The Cliffs - Central Roofing
Minneapolis, Minnesota
Once in a while, every one of us in Tecta
is fortunate to have an opportunity to be part of a project
that turns out to be a great deal of fun - more than anything
the challenge is the fun part.
The project we call, The Cliffs, is owned
by Marfield Belgarde & Yaffe (MBY) Enterprises in Minneapolis,
Minnesota. The Cliffs is an upscale apartment complex with
many of the tenants being professional athletes. The buildings
were originally built in two phases and are only 10 to 15
years old.
The Cliffs consist of 6 buildings, each
with a unique identifying architectural feature of round half
dome roofs over the main living area of the top floor units.
These domes hang over the private balcony decks of each unit
below. There are 26 dome roofs on each building for a total
of
156 dome roofs throughout the entire complex.
The Problem
The relationship between The Cliffs and Central Roofing Company
(CRC) began 3 years ago when CRC started servicing and maintaining
their roofing systems. However, time and time again, during
certain times of the winter months, tenants would experience
leaking from the dome
roofs to built-up roofing connection areas, even though all
the built-up areas appeared to be in satisfactory condition.
CRC started replacing base flashing at the bases of many of
the domes. MBY's costs continued to increase each year for
service and maintenance of these roofs. Water entry into the
building continued to pop up in areas where maintenance had
been completed that appeared to be water tight. When we water
tested areas there would be no water entry. We began to speculate
that the domes may not have been originally insulated properly,
and that there could be a condensation problem.
Working closely with MBY, CRC hired an outside
roofing consultant, Terry Thone from Roof Spec, Inc., and
decided to investigate the problem. Deciding to open up the
domes was a big decision. Once the dome areas were opened
up and the connections to the flat roof areas were exposed,
our speculations were confirmed. The problem was diagnosed
as being condensation and an insulation problem at the dome
roofs. Along with the condensation leaks, were the beginnings
of a mold problem too.
Best Practices
The tough part was not only finding a good solution, but being
diligent to repair only what was needed while meeting a tight
budget. Initially, we specified a complete removal of all
dome roofing and decking, followed by fully insulating the
joist cavities. With 156 domes to open up, every little change
made significant budget differences.
Our pricing ranged from 1 to over 2 million
dollars depending on what MBY and Roof Spec, Inc. decided
would be the best solution. MBY requested a proposal to open
up and apply urethane foam at the connection cavities in order
to close off all sources of air infiltration into the cavities.
Before being awarded the project, we tried this solution on
two domes as a trial and waited through one winter season.
The test roofs performed well.
The budget meetings with Chris Johnson,
a partner at MBY, were long, tedious and little fun. We explored
different roofing systems and budget scenarios. They wanted
the best solution without jeopardizing quality at a reasonable
cost. We ended up insulating key areas, checking other areas
and reroofing all 156 domes with a 60-Mil fully adhered EPDM.
The dome joists were spaced at 12" on center and filled
solid with batt insulation, except at the base. The warm to
cold transition at the deck overhangs and base connection
was determined to be the air infiltration problem. Because
of the infiltration and the fact that these critical areas
were not insulated properly, the dew point temperature was
achieved with the joist space resulting in condensation of
moisture vapor within the joist space. Water would enter the
building appearing to be a roof leak.
Safety was key to setting up for the beginning
stages of this project. We set up extensive safety requirements
and consulted with our safety expert, Ryan Romer. We were
already aware of the dangers on these buildings since a competitor's
roofer fell during the original construction and was killed.
The buildings were built tightly on the sight and the only
access for the overhanging dome roofs was from the roof.
The Solution
First, we needed to tear off all the shingles
from the 156 domes. Second, we scudded back the built up roof
(BUR) areas around the domes in order to cut open the decking
and insulate tightly at the connection. Next, we cut out decking
at the base tie in areas and the end walls, then finished
with solidly spray foam insulating the joist cavities. New
decking was installed as required, and we overlaid the entire
dome roofs with a layer of 1/4" Densdeck board to achieve
a good, bondable roof surface. We then had to again tie-in
the BUR and be careful not to damage the existing BUR that
already had many patches and repairs. Finally, we applied
the new 60-Mil fully adhered roofing system and all new sheet
metal flashing.
The Cliffs project is another great example
of dedication and teamwork of a Tecta America company.
|